Disclaimer Barred Sequencing Claim Delay-damages; Disclaimers

Thursday, November 03, 2005 04:23 pm

 
Disclaimer Barred Sequencing Claim Delay-damages; Disclaimers

A federal court, applying Nebraska law, has ruled that a no-damage-for-delay clause barred an electrical contractor's claim against a construction manager for sequencing changes and interference.

The Omaha Metropolitan Entertainment and Convention Authority retained Kiewit Construction Co. to serve as construction manager on a convention center project. Kiewit committed to a guaranteed maximum price for the work. Kiewit then negotiated guaranteed maximum price subcontracts with a number of trade contractors, including Capital Electric Construction Co., Inc.

The agreement between K [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team