No Bid Correction After Contract Award Bids-mistakes; Equitable Relief

Monday, October 03, 2005 04:11 pm

 
No Bid Correction After Contract Award Bids-mistakes; Equitable Relief

A Tennessee court has ruled that a contractor was not entitled to correct a mistaken bid price after contract award.

HTI Memorial Hospital Corp. solicited bids for construction of a pumping station and water line to service a new hospital facility near Nashville. The bid schedule included quantities of work to be unit priced and then extended for line item totals. But the solicitation contemplated the award of a fixed-price contract. The unit prices were to be used for pricing change orders.

Eatherly Construction Co. submitted a bid on the contract. For the line item of 705 linear feet of 12-inch [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team