Board Addresses 9-11 Base Closure Delay-compensable; Site Access

Friday, December 03, 2004 03:20 pm

 
Board Addresses 9-11 Base Closure Delay-compensable; Site Access

The Armed Services Board of Contract Appeals has ruled that denial of site access following the September 11 terrorist attacks would be compensable unless the base closure was "public and general" in nature.

The Army Corps of Engineers awarded a contract to Conner Brothers Construction Co., Inc. to build a headquarters facility for the 75th Ranger Regimental Compound at Fort Benning, Georgia. The Ranger Compound was fenced off within Fort Benning and was a controlled access area. The contract included a standard Sus [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team