Spatial Problems Caused By Improper Coordination Plans And Specifications; Coordination

Friday, December 03, 2004 03:20 pm

 
Spatial Problems Caused By Improper Coordination Plans And Specifications; Coordination

The Armed Services Board of Contract Appeals has ruled that spatial problems were caused not by lack of government design detail, but rather by improper coordination by the contractor.

M. A. Mortenson Company held a contract for construction of a medical facility at Elmendorf Air Force Base in Alaska. The contract stated that the contractor was [...]

 