California Lien Waiver Applied To Unpaid Work Liens; Waiver

A California court has ruled that the state's statutory conditional lien waiver form released mechanic's lien and bond rights for labor and materials furnished up to the stated date, regardless of whether the contractor actually received payment.

The City of Chico awarded a contract to Monterey Mechanical Co., Inc. for expansion of the municipal wastewater treatment plant. Monterey subcontracted the electrical work to Stratton Electric, Inc. which in turn subcontracted the instrumentation and controls to Tesco Controls, Inc.

Each time Tesco applied for progress payments, Stratton required Tesco to sign a conditional waiver [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team