Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Contractor Waived Progress Payment Procedures Payment-progress; Waiver

Sunday, October 03, 2004 02:54 pm

 
Contractor Waived Progress Payment Procedures Payment-progress; Waiver

A federal court has ruled that a prime contractor waived the progress payment provisions of a subcontract. The prime could not use the sub's noncompliance to excuse nonpayment.

The Department of Veterans Affairs awarded a contract to John Edwards Construction Co. for renovation of a hospital in Hines, Illinois. Edwards subcontracted the fabrication and erection of the structural steel to Advance Iron Works, Inc. The subcontract incorporated AIA Document A201, "General Conditions of the Contract for Construction."

The General Conditions called for Edwards to make monthly [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team