Early Completion And Eichleay Claims Denied Delay-damages; Overhead; Schedule

The Court of Federal Claims has rejected a contractor's claim that the government prevented scheduled early completion and caused the contractor to incur unabsorbed home office overhead.

The Army Corps of Engineers awarded a contract to Jackson Construction Co., Inc. for construction of a new building at the Cold Regions Research and Engineering Laboratory in Hanover, New Hampshire. The fixed-price contract required Jackson to complete the work within 520 calendar days. Jackson prepared two in-house intended schedules: a 14-month schedule [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close