No Delivery Orders Issued Under "Requirements"Contract Project Financing

The Armed Services Board of Contract Appeals has held the government not liable for failing to issue any delivery orders under a "requirements"type contract for asbestos removal. No funds were appropriated for the contract.

The Army awarded a contract to L & C Europa Contracting Co., Inc. to provide all the asbestos removal [...]

 