California Contractor Recovers Eichleay Damages Overhead; Delay-damages

Friday, September 03, 2004 02:44 pm

 
California Contractor Recovers Eichleay Damages Overhead; Delay-damages

A California court has allowed a contractor to recover unabsorbed home office overhead calculated according to the Eichleay formula.

The California Department of Transportation awarded a contract to Heritage Engineering Construction, Inc. to build a sound wall along a freeway. The contract mandated completion within 210 calendar days. The standard Caltrans specifications required the contractor to submit all claims arising from the work within 30 days of receipt of Caltrans' proposed final estimate of payment due.

Work was suspended due to errors in the plans and specifications, as well as the resulting [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team