The Department of Agriculture Board of Contract Appeals has ruled that the government did not improperly interfere with subcontractor relations when it insisted the contractor pay a sub for work the contractor had certified for progress payment purposes.

The U.S. Forest Service awarded a contract to V & W Construction and Services Co. to renovate and expand a d [...]

 