Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Nevada Court Recognizes "No-damage-for-delay"Exceptions Delay-damages; Disclaimers

Saturday, July 03, 2004 01:34 pm

 
Nevada Court Recognizes "No-damage-for-delay"Exceptions Delay-damages; Disclaimers

The Nevada Supreme Court has enumerated the exceptions to the enforceability of "no-damage-for-delay" clauses that are, and are not, recognized in that state.

Las Vegas Sands, Inc. awarded a contract to Lehrer McGovern Bovis, Inc. (LMB) to construct an expansion to an exposition center. LMB negotiated a subcontract with J.A. Jones Construction Co. for performance of the concrete work. The subcontract contained a no-damage-fordelay clause, a portion of which is quoted below.

"Contractor expressly agrees not to make, and hereby waives, any claim for damages, including those resulti [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team