Cm May Be Liable For Schedule Misrepresentation Multiple Prime Contracts; Schedule

Saturday, July 03, 2004 01:34 pm

 
Cm May Be Liable For Schedule Misrepresentation Multiple Prime Contracts; Schedule

The Kentucky Supreme Court has ruled that a trade contractor with no direct agreement with a construction manager (CM) could sue the CM for alleged negligent misrepresentation of the schedule.

DeLor Design Group, Inc., owner of a commercial building, awarded a contract to Presnell Construction Managers, Inc. to serve as the CM in the renovation of the property. DeLor subsequently awarded a contract to EH Construction, LLC for general trade work.

The AIA contract form utilized by DeLor and EH Construction contained the following provision: "The Contractor agrees that nothing in the Cont [...]

 