No Proof Of Pre-bid Reliance Required Plans And Specifications; Changes-constructive

Saturday, April 03, 2004 12:34 pm

 
No Proof Of Pre-bid Reliance Required Plans And Specifications; Changes-constructive

The Armed Services Board of Contract Appeals has rejected the government's contention that "typical wall details"applied to some walls but not others. And because the contract was unambiguous, the contractor was not required to prove pre-bid reliance on its interpretation of the drawings.

The Army Corps of Engineers awarded a contract to Moore & Cowart Contractors, Inc. (M & C) for construction of a series of flood control basins and waterways in El Paso County, Texas. The drawings for vertical walls referred [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close