Consultant Fee Compensable If Necessitated By Change Changes-directed; Schedule

Tuesday, February 03, 2004 11:57 am

 
Consultant Fee Compensable If Necessitated By Change Changes-directed; Schedule

The U.S. Court of Federal Claims has ruled that a contractor's cost of retaining a scheduling consultant would be compensable if it was necessitated by a government contract modification, but not if it resulted from compliance with contractual sequencing requirements.

The Navy awarded a contract to P. R. Burke Corporation for improvements to a sewage treatment plant at Camp Pendleton, California. The contract required that the plant remain in continuous operation during the performance of the work. The contract did not specify a particular sequence of work, but instructed Burke to submit a proposed constructio [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team