Consultant Fee Compensable If Necessitated By Change Changes-directed; Schedule

Tuesday, February 03, 2004 11:57 am

 
Consultant Fee Compensable If Necessitated By Change Changes-directed; Schedule

The U.S. Court of Federal Claims has ruled that a contractor's cost of retaining a scheduling consultant would be compensable if it was necessitated by a government contract modification, but not if it resulted from compliance with contractual sequencing requirements.

The Navy awarded a contract to P. R. Burke Corporation for improvements to a sewage treatment plant at Camp Pendleton, California. The contract required that the plant remain in continuous operation during the performance of the work. The contract did not specify a particular sequence of work, but instructed Burke to submit a proposed constructio [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close