Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Delay Claim Arose "Under The Contract" Claims Administration

Tuesday, February 03, 2004 11:57 am

 
Delay Claim Arose "Under The Contract" Claims Administration

A North Carolina court has ruled that a contractor's claim for delay damages and defective design documents arose "under the contract"for purposes of a statutory waiver of the Department of Transportation's sovereign immunity.

The North Carolina DOT awarded a contract to Battle Ridge Companies to widen and relocate a section of highway in Watauga County. Upon completion of the project, the DOT withheld $233,850 in liquidated damages. Battle Ridge responded by filing a verified claim with the State Highway Administrator seeking remission of the liquidated damages plus more than $2.4 million in increased cost [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close