Control Wiring Was Implicit Contract Requirement Plans And Specifications; Changes-constructive

Saturday, January 03, 2004 11:49 am

 
Control Wiring Was Implicit Contract Requirement Plans And Specifications; Changes-constructive

The Department of Veterans Affairs Board of Contract Appeals has ruled that even though control wiring for the auxiliary power system was not shown on the drawings, the contract when read as a whole - requiring a complete operating system - included the control wiring.

The VA awarded a contract to De Maria Building Co., Inc. to construct a cli [...]

 