Board Rejects "Total Cost" For Idle Equipment Suspension Of Work; Damages

Saturday, January 03, 2004 11:49 am

 
Board Rejects "Total Cost" For Idle Equipment Suspension Of Work; Damages

The Armed Services Board of Contract Appeals has ruled that a contractor could not use the "total cost" method to quantify an idle equipment claim because the contractor had contributed to the problem through its own inefficient management of the equipment.

The Army Corps of Engineers awarded a contract to T & W Edmier Corp. to excavate [...]

 