Contractor Did Not Sign Off Under Duress Changes-directed; Payment-progress

The Armed Services Board of Contract Appeals has ruled that a contracting officer's statement that he could not pay for extra work that was not included in contract modifications was not a threat to withhold progress payments. The contractor did not [...]

 