Contract Terminated For Convenience Prior To Commencement Termination-convenience; Overhead

Sunday, November 02, 2003 05:46 pm

 
Contract Terminated For Convenience Prior To Commencement Termination-convenience; Overhead

A contractor has been unable to prove its unabsorbed home office overhead costs in a situation where a contract was terminated for convenience prior to issuance of a notice- to-proceed.

The Army awarded a contract to Singleton Contracting Corp. for improvements to the Army Reserve Center in Charlottesville, Virginia. Due to errors in the government's drawings, the Arm [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team