Contract Terminated For Convenience Prior To Commencement Termination-convenience; Overhead

Sunday, November 02, 2003 05:46 pm

 
Contract Terminated For Convenience Prior To Commencement Termination-convenience; Overhead

A contractor has been unable to prove its unabsorbed home office overhead costs in a situation where a contract was terminated for convenience prior to issuance of a notice- to-proceed.

The Army awarded a contract to Singleton Contracting Corp. for improvements to the Army Reserve Center in Charlottesville, Virginia. Due to errors in the government's drawings, the Arm [...]

 