"Clerical Mistake"Included Misinterpretation Bids-mistakes; Bonds-bid

Thursday, October 02, 2003 05:37 pm

 
"Clerical Mistake"Included Misinterpretation Bids-mistakes; Bonds-bid

The Idaho Supreme Court has ruled that a "clerical mistake"in a bid included the misinterpretation of a phrase used by a subcontractor in its quotation. The bidder could withdraw its bid without forfeiture of the bid bond.

The Idaho Transportation Department solicited bids for a highway construction project in Bonner County. Westway Construction, Inc. was preparing to bid on the contract. Westway obtained price quotations from two asphalt subcontractors and incorporated the lower price, from Acme Materials and Construction Co., into its bid.

Westway submitted the low bid, accompanied by a five percent bid bond, as requ [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team