Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

"Total Cost" Not Allowed For Lost Productivity Delay-damages

Tuesday, September 02, 2003 05:23 pm

 
"Total Cost" Not Allowed For Lost Productivity Delay-damages

A federal court has ruled that a subcontractor could not use the "total cost method" to calculate lost productivity damages allegedly incurred as a result of prime contractor delay.

The Chester Housing Authority awarded a contract to C & C Rehab and Construction, Inc. for the construction of a housing project in Chester, Pennsylvania. C & C subcontracted the concrete foundation work, as well as curbs and sidewalks, to Net Construction, Inc.

The project was plagued by delay and was completed well behind schedule. Net Construction sued C & C for the loss it incurred on the subcontract. N [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team