Construction Manager Functioned As General Contractor Bonds-payment; Suppliers

Tuesday, September 02, 2003 05:23 pm

 

The Rhode Island Supreme Court has allowed a supplier to proceed against a payment bond even though the prime contract called for "construction management services" and required trade contractors to provide their own bonds.

The Warwick School Committee awarded a contract to Berkshire Construction Services, Inc. for construction management services on a school building project. The contract called for Berkshire to furnish a payment bond covering only the construction management services, with the trade contractors each responsible for providing their own payment bo [...]

 