Court Addresses "Commission" On Subcontracted Changes Changes-directed; Overhead

Saturday, August 02, 2003 03:19 pm

 
Court Addresses "Commission" On Subcontracted Changes Changes-directed; Overhead

The U.S. Court of Federal Claims has ruled that the "commission"on subcontracted work, authorized by the GSA Equitable Adjustment clause, is set at ten percent. It is not calculated by adding the contractor's overhead and profit.

The General Services Administration awarded a contract to North American Construction Corp. (NACC) for renovation of the federal building in Sacramento, California. During the course of the work, GSA issued a series of change orders. Much of the changed work was performed by subcontractors to NACC. A dispute developed r [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team