Mechanic's Lien Could Not Cover Delay Damages Liens; Delay-damages

Wednesday, July 02, 2003 03:08 pm

 
Mechanic's Lien Could Not Cover Delay Damages Liens; Delay-damages

The Nevada Supreme Court has ruled that a mechanic's lien only secured payment up to the contract price. The lien could not include delay damages in excess of that price.

Amedeo Vegas I, Inc. awarded a contract to R. D. Olson to construct a commercial project. Olson subcontracted the framing and drywall work to California Commercial Enterprises (Commercial). During the course of the project, Olson issued a series of written change orders which greatly increased the subcontract price. At the completion of its work, Commercial filed a mechanic's lien on the project for the balance of the adjusted [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close