Takeover Surety Had No Recourse With Board Termination-default; Bonds-performance

Wednesday, July 02, 2003 03:08 pm

 
Takeover Surety Had No Recourse With Board Termination-default; Bonds-performance

The Armed Services Board of Contract Appeals has ruled that a surety for a defaulted contractor could not file a claim under the Contract Disputes Act for an improper payment to the contractor made prior to a takeover agreement. And the takeover surety could not recover for government delay because no new schedule had been established.

The Air Force awarded a contract to Castle Abatement Corp. to r [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team