Owner Waived Change Order And Notice Requirements Changes-directed; Waiver

Wednesday, July 02, 2003 03:08 pm

 
Owner Waived Change Order And Notice Requirements Changes-directed; Waiver

A Missouri court has ruled that a project owner lost the right to enforce requirements for written change orders and notice of cost overrun when the owner repeatedly issued oral directives for additional work.

DLJ Properties, Inc. awarded a contract to Staat Construction Co. to build an office complex in Jefferson County. Under the terms of the cost-plus contract, Staat guaranteed a maximum price of $1,600,252. The drawings and specifications included an attachment with a series of cost estimates for the various elements of the project.

The construction contract requir [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team