Shopping Cart (0) items Sign In

Construction Claims Monthly - Devoted exclusively to the problems of construction contracting since 1963

‹ Prev article: 
 

Bid Rejected Due To Undisclosed Scheduling Requirement Bids; Schedule

Friday, May 02, 2003 02:48 pm

 
Bid Rejected Due To Undisclosed Scheduling Requirement Bids; Schedule

The Kansas Supreme Court has ruled that a public project owner improperly rejected a low bid based upon scheduling requirements not disclosed in the bid solicitation.

The City of Deerfield issued an invitation for bids for a street improvement project. The solicitation instructed bidders to submit a commencement date no later than October 17, 2000. Project completion was required within 75 days of commencement of the work. The contract was to be awarded to "the lowest responsible, responsive bidder."

Ritchie Paving, Inc. submitted the low bid. Ritchie specified a commencement date of October 1, 2000. The C [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team