Extension Created Presumption Of Responsibility Delay-compensable

Wednesday, April 02, 2003 01:02 pm

 
Extension Created Presumption Of Responsibility Delay-compensable

The Armed Services Board of Contract Appeals has ruled that when the government extended the contract completion date by 51 calendar days, it created a rebuttable presumption that the government was responsible for the delay.

The Navy awarded a contract to The Sherman R. Smoot Corp. for demolition, renovation and new construction of buildings at the Washington Navy Yard. The Nav [...]

 