Sunday, March 02, 2003 12:46 pm

 
Drainage Work Needed To Meet Design Criteria Changes-constructive

The Armed Services Board of Contract Appeals has ruled that storm drainage work was not a constructive change in a design/build contract. The work was needed to comply with specified design criteria.

The Corps of Engineers awarded a contract to Wade Perrow Constr [...]

 
› Next article: 
 