Total Cost Method Disallowed Claims Administration

Sunday, March 02, 2003 12:46 pm

 
Total Cost Method Disallowed Claims Administration

The Armed Services Board of Contract Appeals has refused to allow a contractor to use the "total cost method" to price a claim. The contractor could not prove the reasonableness of its bid price or its own lack of contribution to the cost overrun.

The Navy awarded a contract to Management Resource Associates, Inc. (MRA) for boiler repairs and replacement of piping systems in a building at Oceana Naval Air Station in Virginia Beach, [...]

 
› Next article: 
 
Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close
 
×

Dear Valued Customers,

We regret to announce that ProEdTech LLC and all its affiliate brands will cease operations on April 1, 2019.

We are no longer able to fulfill online orders. We will fullfill all DVD and book orders already placed.

Customers of canceled webinars and subscription products may request a refund at (800) 223-8720 or service@proedtech.com. You must do so by April 1, 2019.

Thank you for your business and loyalty over the years. We sincerely apologize for any inconvenience caused.


Best regards,
The ProEdTech Team