Utility Obligated To Mark Buried Lines For Contractor Negligence; Delay-damages

Sunday, February 02, 2003 12:36 pm

 
Utility Obligated To Mark Buried Lines For Contractor Negligence; Delay-damages

An Illinois court has ruled that a telephone company had a statutory duty, but no common law duty, to mark underground utilities in order to avoid delaying a highway contractor.

The Illinois Department of Transportation awarded a contract to Plote, Inc. to make improvements to a highway in Arlington Heights. The DOT asked Illinois Bell Telephone Company, on several occasions, to indicate on the construction drawings the location of underground telephone lines. The DOT told the phone company the scheduled date of commencement of construction. Illinois Bell was not particularly respo [...]

Sign up now for Construction Claims Monthly Online! Your own virtual help desk of must-have techniques, tutorials, and how-to articles.
 
Join Now Construction Claims Monthly! Close